- RAK ROCK COMPANY
- P.O.BOX 86
- RAS AL KHAIMAH
- UNITED ARAB EMIRATES
| TEL.: |
00971-7-226 8 251
|
| FAX.: |
- 00971-7-266 8 994
|
-
|
| Prevention of dust emissions at ship loading. |
| Material to be handled: |
LIMESTONE |
| Handling capacity: |
2.500 tons |
| Granularity: |
0 - 32 mm |
|
|
|
 |
 |
|
|
| The following operation points in the conveying belt system between the storage silos and the transfer point from the loading chute into the ships hold will be sprayed: |
|
| ...the transloading points silo Þ discharge conveyor which are equipped with |
|
|
| ...the transloading point silo discharge conveyor Þ feeding conveyor to |
|
|
| ...the transloading point transvers conveyor inside the shiploader |
|
|
| ...the transfer point discharging pipe Þ ships hold |
|
|
| The maximum mixture capacity of the ECS installation is 6.000 litres per hour |
| The actual quantity of service fluids used is: |
| power drain |
|
4.500 |
litres of water per hour |
|
1,13 |
litres of tenside per hour |
|
5,5 |
kw |
|
|
|
| Related to the handling capacity of 2.500 tons per hour the additional humidity in the Material is 0.18% |
|
|
| The proportion of dust still remaining in the surrounding air is £ 18mg/m³ |